BuildingSalem

SALEM216_BuildingSalem_Concepts_V2r4-page-001

Updates on the Canal Street Flood Control project in #SalemMA:

General Project Information:

• Project work hours: 7am – 3:30pm. The City’s contractor is P. Gioioso & Sons of Hyde Park, MA.

• Traffic throughout the neighborhood is anticipated to be alternating two-way with police details. Entrances to houses and adjacent roads may be impacted during the construction. Parking will not be allowed on either side of the road at or near the work zone. Roads will be open during non-working hours.

• Roadway work is anticipated to be limited during the winter months due to weather concerns (January through March).

Projected Construction Activities:

Week of February 19th
• The Contractor will continue the Forest River Park retaining wall installation, and drainage swale work.
• The Contractor will begin to install the Forest River Park ball field dugout and concession stand foundations.

Week of February 26th
• The Contractor will continue to install the Forest River Park Ballfield dugout and concession stand foundations.
• The Contractor will continue the Forest River Park ball field, pedestrian bridge, and drainage swale work.
...

Essex Street Utility Project in #SalemMA

Two Week Look Ahead : February 12th – February 23rd

Projected Construction Activities:

Week of February 12th
• The Contractor will continue Sewer and Drain improvements.
• There will be No Parking on both sides of Essex between Summer Street and Crombie Street during the day.
• Daytime road closures may be required to complete this work. Every attempt will be made to minimize any road closures.
• Detour signage will direct traffic around work zone, traffic and pedestrian signs will be placed throughout the project limits.

Week of February 19th
• No Work on Monday Feb 19th (Presidents Day)
• The Contractor will continue Sewer and Drain improvements.
• There will be No Parking on both sides of Essex between Summer Street and Crombie Street during the day.
• Daytime road closures may be required to complete this work.
• Detour Signage will direct traffic around work zone, traffic and pedestrian signs will be placed throughout the project limits.
• If all goes well, the work from Summer Street to Crombie Street will be completed during this week.
...

The City of #SalemMA is carrying out repairs and upgrades to the sanitary sewer system on Beckford Street between Federal Street and Bridge Street over the next few weeks. See notice for details. ...

Two-week look ahead for work on the Essex Street Utility Project in #SalemMA:

Week of February 5th
• The Contractor will continue Sewer and Drain improvements.
• There will be No Parking on both sides of Essex between Summer Street and Crombie Street during the day.
• Daytime road closures may be required to complete this work. Every attempt will be made to minimize any road closures.
• Detour signage will direct traffic around work zone, traffic and pedestrian signs will be placed throughout the project limits.

Week of February 12th
• The Contractor will continue Sewer and Drain improvements.
• There will be No Parking on both sides of Essex between Summer Street and Crombie Street during the day.
• Daytime road closures may be required to complete this work. Every attempt will be made to minimize any road closures.
• Detour signage will direct traffic around work zone, traffic and pedestrian signs will be placed throughout the project limits.
...

A reminder that steam blows that are a component of the commissioning of Unit 5 at the Footprint power plant are scheduled to commence today and will take place on days throughout the next two weeks. Those in #SalemMA near the plant may hear loud noises or see plumes of steam during this work. This is not representative of what will be normal plant operations and is only for the commissioning process. ...

SHARE

CONNECT WITH US

BuildingSalem Twitter BuildingSalem Facebook BuildingSalem Rss