BuildingSalem

SALEM216_BuildingSalem_Concepts_V2r4-page-001

22 hours ago

BuildingSalem

Note that Canal Street paving work in #SalemMA has been cancelled for tonight. Overnight work is scheduled to resume Wednesday night and conclude Thursday night, weather permitting. ...

6 days ago

BuildingSalem

Final paving on the Canal Street corridor in #SalemMA is currently scheduled to begin on Sunday, September 16, overnight. The work is anticipated to take approximately four nights to complete, weather permitting. Line striping and crosswalk installation will take place within the next two to three weeks following the completion of paving. ...

7 days ago

BuildingSalem

Cloverdale, Greenlawn, Glenn, Springside Avenues, Porcello
Lane Water Improvement Project in #SalemMA
Two Week Look Ahead: September 10th – September 21st

Projected Construction Activities:

Week of September 10th
 The contractor will continue installing water services on
Cloverdale and Springside Avenues.
 The contractor will remove temporary bypass piping on
Cloverdale and Springside Avenues.
 The contractor will be doing some drain work at Cloverdale Ave and Marlborough Road.

Week of September 17th
 The contractor will begin removing construction equipment from the area of Cloverdale and Springside Avenues.
 The contractor will be installing loam and seed on Cloverdale and Springside Avenues.
...

1 week ago

BuildingSalem

Memorial Drive, Victory Road, and Szetela Lane Utility Improvement Project in #SalemMA
Two Week Look Ahead: September 10th – September 21st

Projected Construction Activities:

Week of September 10th
• The contractor will be pouring sidewalk panels on Memorial Drive, Victory Road and Szetela Lane.
• The contractor will be removing equipment from job site and begin cleaning up work areas.
• The contractor will install loam and seed.

Week of September 17th
• The contractor will continue to remove equipment and clean up construction areas.
...

1 week ago

BuildingSalem

Orleans Ave, Crosby and Verdon Streets Water Improvement Project in #SalemMA
Two Week Look Ahead: September 10th – September 21st

Projected Construction Activities:

Week of September 10th
• The contractor will be installing loam and seed
• The contractor will be cleaning up construction area

Week of September 17th
• The contractor will be off site
...

SHARE

CONNECT WITH US

BuildingSalem Twitter BuildingSalem Facebook BuildingSalem Rss