BuildingSalem

SALEM216_BuildingSalem_Concepts_V2r4-page-001

Updates from Salem State University:

Off-Hour Work
Daniel O’Connoll Sons will be continue to work on steel erection and enclosing the building for the Mainstage Theatre this Saturday, February 13, 2016 starting at 8 a.m. There is no construction work expected on Monday, February 15.

Sophia Gordon Center for the Creative and Performing Arts
Contractors continue to work on the interior steel erection and exterior enclosure of the building. This is expected to be the major activity for the next couple of weeks. The contractor is expecting to have the building enclosed this spring.

The contractor is still in the process of coordinating the installation of two new electrical poles in front of the Mainstage Theatre as part of this project. The schedule is dependent on National Grid, but we anticipate that the poles are likely going to be installed in Saturday, February 20. National Grid prefers to do this work on a Saturday to reduce the impact on traffic. There is no expected outage with the installation of the poles. Work related to switching the power over to the new poles will not occur until later this spring, likely sometime in May, pending National Grid’s schedule. This is the only work that may cause an outage. National Grid is in the process of determining if this work can be done with no outage to neighboring homes. We have asked National Grid to keep us informed with as much advanced notices as possible as this process moves forward so that we can keep everyone updated.


NORTH CAMPUS PLANNING STUDY
In partnership with the Massachusetts State College Building Authority (MSCBA), the university will release an RFP in the coming month to solicit a planner to help us evaluate our master plan for North Campus with consideration of the campus center, housing needs, and academic programming as it relates to the relocation of South Campus to North Campus. This study will also evaluate the potential relocation of the Horace Mann Laboratory School to South Campus. As the study moves forward, there will be ample opportunity for the internal and external campus communities to provide input. The scope of the RFP will be reviewed at the SSUNAC meeting on February 17.
...

Updates from the Salem Cable Project:

By the end of the day on tomorrow all cable splicing on Washington Square South is expected to be complete. At the Hawthorne Boulevard manholes, contractors have begun cable splicing, and expect to complete their work towards the end of next week.

Cable pulling is expected to begin tomorrow on Congress Street. As you know this process takes about one week to complete. Once installed, the next step will be to splice the cables inside he manholes. This work is scheduled to begin during the last full week in February, and be complete by the end of the month -- or shortly thereafter.

Cable installation on Fairfield Street is slightly ahead of the operation on Congress Street. With one section of cable already installed between the Fairfield manholes and the Canal Street Station, early next week contractors will begin to install cables connecting the Fairfield Street manholes to the manhole locations on Congress Street. Splicing at the Fairfield manholes will start once installation is complete, and is expected to be finished by the beginning of March.

As we get closer to cable removal in the spring, our outreach team will be out advising neighbors and businesses about the upcoming work, and working to mitigate inconveniences from construction to the greatest extent feasible.
...

SHARE

CONNECT WITH US

BuildingSalem Twitter BuildingSalem Facebook BuildingSalem Rss