Canal Street Flood Control

Two Week Look Ahead: October 23-November 3

Project work hours: 7am – 3:30pm. Traffic throughout the neighborhood is anticipated to be alternating two-way with police details. Entrances to houses and adjacent roads may be impacted during the construction. Parking will not be allowed on either side of the road at or near the work zone. Roads will be open during non-working hours.

Projected Construction Activities:

 

Week of December 11 ·        The Contractor will be installing water services on Forest Ave and connecting the new water main to the system on Canal St.

·        The Contractor will be installing a new drainage system on Lussier St.

·        The Contractor will be installing curb and sidewalks on Forest Park Drive.

·        The Contractor will continue the Forest River Park Ballfield, pedestrian bridge and drainage swale work.

Week of December 18 ·        The Contractor will be installing curb and sidewalks Forest Park Drive.

·        The Contractor will pave Forest Ave with temporary asphalt for the winter.

·        The Contractor will continue the Forest River Park Ballfield, pedestrian bridge, drainage swale work, and the outlet to the ocean.

Project Background

The area from St. Paul Street to Forest Avenue in Salem along Canal Street is susceptible to flooding, with over 30 acres and 50 buildings impacted by 1% storm events.Project Summary

The City has completed a number of utility improvements as part of Phase 1 of the overall drainage improvement to address this flooding. The Phase 1 improvements concluded in December 2014. Following the Phase 1 improvements, the City is reconstructing, with state funding, the Canal Street roadway from Mill Street to Jefferson Avenue. Phase 2 of the drainage improvements are now underway.

For more information about the project, visit the Salem City Engineer’s Canal Street project website.

SHARE

CONNECT WITH US

BuildingSalem Twitter BuildingSalem Facebook BuildingSalem Rss